Error message examples
Unrecognized value to the «dateUnit» parameter in Function Sequence: 'hr' Possible values are: 'Y', 'Q', 'M', 'WD', 'D', 'h', 'm', 's'
Cause
You have passed an unrecognized value as the «dateUnit» parameter to the Sequence function. «DateUnit» parameter can be specified to generate a sequence of dates, and the accepted values to the parameter are:
'Y' : Years 'Q' : Quarters 'M' : Months 'WD': Weekdays 'D' : Days 'h' : Hours 'm' : Minutes 's' : Seconds
The following code creates a date sequence from 1-Jan-2009 to 31-Dec-2010 with a step of 4 months.
Sequence(MakeDate(2009, 1, 1), MakeDate(2010, 12, 31), 4, dateUnit: "M") →
[1-Jan-2009, 1-May-2009, 1-Sep-2009, 1-Jan-2010, 1-May-2010, 1-Sep-2010]
Please click on the following link to learn more about the optional «dateUnit» parameter.
Remedies
Correct the «dateUnit» parameter passed to the Sequence function to a recognized value given above.